Scope of Work:A former printing press and gin distillery Laser House situated near the Barbican in central London, has undergone a multi-million-pound makeover by one of our most prestigious clients.
COLUMN REPAIR AND CFRP STRENGTHENING
Duration:
2 Weeks
Project Details
The Challenge
This prestigious development required partial demolition of the existing structure and construction of extensions to the existing building, CCUK were part of the delivery team charged with providing the right, structural strengthening solution in key effected areas.
Working closely with the main contractor and coordinating with demolition activities CCUK carried out extensive concrete repairs and carbon fibre strengthening to 16 columns throughout the building.
The Solution
Column strengthening consisting of 2 layers of Fibrwrap carbon fibre strengthening system applied in the hoop direction for additional axial loading.
The Result
CCUK delivered another quality project for two of our top clients, on time and to budget. We would like to thank Graham Construction and HTS for their continued, ongoing support.